Commissioning of BPD Solar Pumping Variator

    Commissioning of BPD Solar Pumping Variator

    Good Morning!!

    Today we bring you a video of the start-up of a solar pumping drive.

    This video explains step by step how to connect drives with connection and parameters for both three-phase and single-phase pumps with or without capacitor.

    AC input

    Connection: AC INPUT

    Connections:

    Connect LNT to AC INPUT as indicated on the plug

    AC input

    Connection: AC INPUT

    Connections:

    • Phase 1 Pin 1

    • Phase 2 Pin 2

    • Phase 3 Pin 3

    Buoys

    Connection: COM

    • Buoys Full tank

    • Connections:

    • Cable 1 Pin 3

    • Cable 2 Pin 5 (common)

    • Dead Well

    • Connections:

    • It must be connected between pins 4 and 5

    Solar panels

    Connection: -DC INPUT and + DC INPUT

    Connections:

    Connect Positive and Negative Mc4's to the Inverter.

    Keyboard Connection

    Recommended Parameters

    To enter parameters:

    • We press the PROG.P00 key

    • We move with the arrows to reach the first group.

    • We press DATA/ENT P00.00

    • We move with the arrows until we reach the desired second group parameter and press DATA/ENT

    • By default the value will appear: 0

    • We select the indicated value:1

    • We click on DATA/ENT and continue with the same process for the rest of the parameters.

    Parameters Pump III 230V

    (enter parameters according to established order)

    P00.18 = 1

    P02.00 = 0

    P02.05= Pump amps + 0,2

    P15,05 = 60.0

    P15.17 = 00.0

    P15.21 = 600.0

    P07.04 = 1

    P08.28 = 10

    P08.29 = 710

    P05.01 = 1

    P00.01 = 1

    Single Phase Pump Parameters

    (enter parameters according to established order)

    P00.18 = 1

    P02.00 = 1

    P02.05= Pump amps + 3

    P15,05 = 80.0

    P15.17 = 00.0

    P15.21 = 600.0

    P07.04 = 1

    P08.28 = 10

    P08.29 = 710

    P05.01 = 1

    P00.01 = 1

    After entering the parameters, turn off the drive

    (remove the fuses until Poff appears on the screen and wait 20 seconds)

    Put the Fuses back in and wait 20-30 seconds.

    The drive will start automatically.

    B. Single phase with capacitor (connection: AC OUTPUT)

    Connections:

    • Neutral (blue wire): PIN 2

    • Line (brown wire): PIN 3

    • 3rd Cable not connected to the drive.

    • The colors can vary, you have to use a multimeter to find Line and Neutral.

    • Parameter: P04.34=10

    B. Single-phase without capacitor (connection: AC OUTPUT)

    Connections:

    • Neutral (blue wire): PIN 2

    • Line (brown wire): PIN 3

    • 3rd Wire (black wire): PIN 1

    • The colors can vary, you have to use a multimeter to find Line and Neutral.

    • Parameter: P04.34=11

    We measure the resistance in OHMs between all cable combinations.

    (The colors are only indicative to show how to calculate it)

    Blue-Black = 11

    Brown-Blue=2

    Black-Brown=7

    • We keep the one with the highest value and the one with the lowest value

    • The common color in both is the Line or Phase. (in this case Blue)

    • In the one with the lowest value, the other one that is not Line/Phase is the Neutral. (in this case Brown)

    • The remainder would be the condenser phase

    If you have any questions you can contact us at 854556349 or by email Servicio@wccsolar.es